Case Study

Sanford Success

Sanford, Timaru MP Room Extension

Harding Construction was contracted to complete the Main Processing Room extension for Sanford, Timaru using a steel structure from Coresteel South Canterbury. 
Quality and timing were paramount with this project as it had to meet a stringent food-grade finish in time for the Toothfish harvest. No delays or concessions could be tolerated.

The Challenge

Extending the MP Room at the Timaru factory in time for the toothfish harvest was critical for Sanford Ltd to  meet their 2018 production demands.
Delays confirming final architectural designs meant that the actual build-time available was very tight. 
The date for the first delivery of fish could not be altered. It was up to Harding Construction to find a way to meet the schedule.

The Solution

Careful production planning and project management were key to the success of this project. Key suppliers and contractors committed themselves to meeting the deadlines to make the tight time frames achievable.
All materials were pre-ordered to size, ensuring immediate installation was possible without remeasure once delivered to site. This required stringent planning from the Harding Construction project management team.  
“Our association with Coresteel Buildings meant we were assured that the steel structure would be designed, engineered and manufactured exactly to the specifications needed,” says Simon Harding of Harding Construction and Coresteel South Canterbury. “With no hot works required on site, assembling the kitset was a very efficient process and meant we could very quickly start closing the building in.”

The Process

The hand-picked site team was well aware of the time constraints and need for a food-grade finish. Commitment to ‘doing it once and doing it right’ meant tasks were completed to a high standard without the need for re-work or delay. A dedicated project manager working behind the scenes made critical programme and material supply decisions to ensure the smooth running of the project.
Timely, informative communication was essential. “Everyone needed to know exactly what was going on at all times,” says Harding.  Daily site meetings were held with the build team and the client’s representatives. Detailed written communication and photo records were maintained, along with stringent Quality Assurance checks throughout the process. All phone calls and conversations were followed up with emails.
Harding Construction’s commitment to ensuring the plans and specifications were followed exactly meant that all building inspections were completed without the need for any re-work. “It is because of our effective in-house QA management system that we can achieve this kind of accuracy,” says Harding.
All tasks were carefully thought out before work began. Time and cost-saving initiatives were implemented wherever possible with the aim of achieving maximum efficiency and ensuring a top quality result. 

The Result

The building was successfully completed well before the first toothfish deliveries, enabling early commissioning of the building. The Sanford team was able to install the factory plant in the building and complete all testing well in advance.
“We are delighted with the excellent result we achieved on this project,” says Harding. “The customer is happy, our guys enjoyed the work and we made a good thing happen.”
 

Heaven for Hell

Harding Construction completed the fitout of the new Timaru Hell Pizza premises in July, 2016.

The Challenge

The new restaurant not only had a specific brand standard to achieve, but also required installation of specialised kitchen equipment that had to fit in a relatively confined space.

"It was important that all areas of the restaurant were finished to a high standard, not only reflecting the Hell Pizza brand but also ensuring maximum efficiency in all work spaces," says Simon Harding, Construction Manager for Harding Construction.

Some items took up more space than the plans had allowed for, so the team had to make adjustments once everything was on site and actual measurements could be taken.

Mr O, the proprietor, had a set budget and a set deadline for opening. It was imperative that all work be completed on time and on budget to meet these goals.

The Solution 

Hell pizza kitchen.jpg

"Saving a few centimetres here and there made a big difference" says Harding. Our main issue was that the fridge door hit the extractor hood in the kitchen when it opened. By adjusting the hood we were able to ensure that the fridge door could open freely and avoid damage to either piece of equipment."

Hell pizza inside small.jpg

The Result

Hell Pizza Timaru opened to flocks of enthusiastic customers on the due date. All equipment was installed without fuss and the fitout looked great. 

Mr O was effusive in his praise, "Our thanks to Harding Construction.You are professional and client focused. You gave lots of good advice to save us costs. The most important thing for us was that our project was finished within the set time scheduled." 

 

Hell pizza inside2.jpg

ABCs for ADBT

Getting back to basics  a win for ADBT

Raewyn Bell of Aoraki Development, Business and Tourism approached Harding Construction in March 2015 asking if we would be interested in coordinating the fit-out of their new premises. 

_DSC5743.jpg

With a wry smile, Raewyn made it clear there was a catch: They wanted it done for as close to nothing as possible.  ADBT, she explained, had minimal funding for the project, but needed to vacate their current premises. Would Harding Construction help them?

 

_DSC5731.jpg

There was no doubt in our minds that we would. We rallied the support of other local companies we knew valued ADBT, asking them to join us in providing a high quality commercial fit-out for next to nothing. Their responses were overwhelmingly positive and very humbling. The outcome achieved far more than just the production of a high quality commercial fit-out. 

Harding Construction was extremely easy to work with, providing solutions and options and genuinely understanding our brief. They prepared a complete package that enabled the project to be completed in a timely and cost effective manner. The result is an area where visitors are welcomed into an environment of District pride.

— Wendy Smith, Chief Executive, ADBT

This project brought together a community. It showed that in South Canterbury we value community more highly than dollars. It provided opportunities for innovation, creativity and problem-solving. It allowed for generosity, cooperation and collaboration. It enabled a united show of appreciation of the work and value ADBT brings to our business community.

This project was entered in the 2016 Master Builders Commercial Project Awards, winning a prestigious Special Award overall and  Bronze in the Commercial and Civic section.

Total Project Value             Confidential
Price to Customer              20% of total project value    
Value to the Community    Priceless
 

St Joseph’s School, Temuka - A case study in excellence

The outstanding upgrade of facilities at St Joseph’s School, Temuka achieved a complete transformation that delighted a community and is the envy of others. 

StJosephsphoto2.jpg

St. Joseph’s upgrade an “outstanding” transformation

Harding Construction was contracted by Opus International Consultants on behalf of the Roman Catholic Diocese of Christchurch as the Main Contractor to complete an upgrade of Blocks 3 and 4 at St Joseph’s School, Temuka, in 2014. The contract value for this project was $320,000 (including variations). Work began in August and was completed in November, 2014. 

Students from St Joseph's School celebrate their newly upgraded classroom blocks. 

Students from St Joseph's School celebrate their newly upgraded classroom blocks. 

Our brief for this project was to upgrade the existing classroom blocks, which included demolishing and replacing old walls, ceilings and flooring, creating new storage areas and re-lining classrooms. We co- ordinated sub-trades for painting services, roofing, aluminium joinery, floor coverings, plumbing, drainage and electrical services, and supply of metalwork and concrete work. 

We would like to officially thank you and your team for the outstanding work you completed for us as part of our recent recladding and building upgrades at our school.
— Bernie Leonard, Principal

The new design makes the most of indoor and outdoor learning spaces.


Co-ordination and communication the key to success

As the Main Contractor for this project it was our responsibility to co-ordinate the sub-trades required to complete the work on time, on budget, with no surprises. Our experienced project management team facilitated this with ease, ensuring excellent communication between the school, Opus, the sub- trade contractors and our crew. 

The foreman managed communications with subcontractors very efficiently, ensuring they worked around the needs of the school. At all times the team were efficient, obliging and fun to work with. We also found Simon extremely thorough during the final checks, insisting on every job being completed thoroughly and professionally.
— Bernie Leonard, Principal
The upgrade created safe and easy flow between the classrooms and the rest of the school. 

The upgrade created safe and easy flow between the classrooms and the rest of the school. 


Cost-effective solutions

The scope of the project expanded from the initial quoted work to a significantly larger project as unforeseen structural issues were discovered once work had begun, requiring full and immediate remedy. Our skilled team quickly formulated a time and cost-effective solution for this, and work continued without interruption or delay. 

The revamped classrooms are light, spacious, modern and attractive. 

The revamped classrooms are light, spacious, modern and attractive. 

Throughout the process we found your team to be extremely professional and willing to “go the extra mile” for us. The difficulties that arose from the original plans because of the internal state of the building were managed patiently by the foreman, who communicated extremely well with the project managers and myself.
— Bernie Leonard, Principal

The Harding Construction Team is safe, considerate and professional

At all times, our work and site safety practices were keyed to the fact that we were conducting construction work in a busy primary school with curious children all around, and teachers wanting to continue their classroom programmes with minimal disruption.

Harding Construction has an excellent Health and Safety record. All projects have an individual Site Specific Safety Plan tailored to meet the specific needs of that site. Our experienced team is well- versed in ensuring work on school sites is completed in as safe and unobtrusive a manner as possible. 

The building team were extremely safety conscious with the safety board very visible capturing our students’ attention, safe driving in and out of the school during school hours and limited interruptions with noise.
— Bernie Leonard, Principal
Clean lines and a modern look transformed tired buildings into a 21st Century learning environment 

Clean lines and a modern look transformed tired buildings into a 21st Century learning environment 


Great to work with

Staff from the school were effusive in their praise for our team’s professional conduct and the way they worked in with the needs of the school. This was a very successful project with an excellent result. 

Staff found your team great to work with. The guys also sparked ideas for our young builders in our tech shed.
— Bernie Leonard, Principal
Harding Construction Management were guests of honour at the school celebration blessing the finished buildings. 

Harding Construction Management were guests of honour at the school celebration blessing the finished buildings. 

The whole community is delighted with the final outcome of a complete transformation of a building that is the envy of others.
— Bernie Leonard, Principal